For Property Renovation & Maintenance

Alexandra Park Precinct,

Auckland — Stages 1 & 2

Head Contractor

CMP, Demellans

Client / Asset Owner

Alexandra

Location

Alexandra Park Precinct, Greenlane / One Tree Hill, Auckland

Duration

14 Weeks

Scope of Work

External environment and public realm works surrounding high-rise residential buildings, including footpaths, urban channels, gardens, and associated hard landscaping within a mixed-use precinct.

Key challenges

Delivery of works across two separate stages under different head contractors

High-end external finishes forming the primary visual interface for residential buildings

Live environment with public access to cafes, restaurants, and pedestrian areas

Ongoing vehicle movements and deliveries servicing active hospitality tenancies

media-image (1)media-image (2)

How we handled it

Works were carefully planned and sequenced to manage the interface between construction activities and public access requirements.

Pavecraft coordinated closely with the head contractors to maintain safe pedestrian and vehicle movement while delivering works adjacent to operating hospitality venues.

Our team managed transitions between completed and active zones, ensuring continuity of access and minimising disruption throughout both stages. The experience gained during Stage 1 supported efficient delivery and site familiarity during Stage 2.