For Property Renovation & Maintenance

Auckland City Council

Pedestrian Works

Head Contractor

Auckland City Council

Client / Asset Owner

TCM

Location

Orewa, Auckland

Duration

14 Weeks

Scope of Work

Pedestrian-focused public works using clay paving, including footpaths and associated kerb and channel works within an active town centre environment.

Key challenges

Live pedestrian environment requiring continuous public access

Active retail and business frontage operating throughout construction

Tight working areas requiring staged and non-linear sequencing

High level of pedestrian and traffic management requirements

media-image (1)media-image (2)

How we handled it

Works were planned and sequenced to maintain uninterrupted access to shops and businesses throughout the project.

Paving activities were staged to allow sections to be paused, bypassed, and reinstated in line with trading requirements and pedestrian flows.

Our team coordinated closely with site traffic and pedestrian management to ensure safety, access, and continuity of movement while work progressed.

The Project Result